County Regulations

Georgetown County, SC Stormwater Regulations

Georgetown County holds a Phase II Small MS4 NPDES permit and faces unique stormwater challenges from its position at the convergence of four major river systems. Hurricane and riverine flooding regularly tests stormwater infrastructure. SCDES enforces state penalties up to $10,000 per day, with county floodplain regulations adding another layer of compliance.

verified Last verified: March 2026

Primary source: South Carolina Department of Environmental Services (SCDES)

Quick Reference

Category Details
Regulatory Authority SCDES (state), Georgetown County Planning & Development (local), OCRM (coastal)
MS4 Status Phase II Small MS4
Permit Required State: 1 acre+ disturbance (NPDES CGP). OCRM permits for coastal/tidal areas
Inspection Frequency Construction: weekly + after 0.5" rain. Post-construction: annual BMP inspections
Penalty Range State: up to $10,000/day per violation
Coastal Designation Yes. Extensive tidal and coastal areas, including Winyah Bay, Pawleys Island, Litchfield Beach
Key Municipalities City of Georgetown, Pawleys Island, Andrews

Permit Requirements

Georgetown County follows the state NPDES Construction General Permit requirement: projects disturbing one acre or more must obtain permit coverage from SCDES. A Stormwater Pollution Prevention Plan (SWPPP) is required that details erosion and sediment controls for construction and permanent post-construction BMPs.

The county's extensive coastal zone, including Winyah Bay, the Waccamaw Neck area (Pawleys Island and Litchfield Beach), and tidal marshes, requires OCRM Critical Area Permits for development activity. Properties along the Waccamaw River, Pee Dee River, and their tributaries may also fall within regulated areas.

Georgetown County's floodplain regulations add another permitting layer. A large percentage of the county falls within FEMA-designated flood zones due to the four-river system. Development within these zones requires floodplain development permits and may trigger compensatory storage requirements.

Inspection Obligations

Active construction sites must be inspected weekly and within 24 hours of any rainfall of 0.5 inches or more. The NPDES permit requires documented inspections that record the condition of all erosion and sediment control measures.

Post-construction BMP inspections are required annually by the property owner or responsible party. Georgetown County may conduct its own inspections of permitted facilities, particularly after major storm events that could damage or compromise stormwater systems.

After hurricanes and major flooding events, the county conducts rapid assessments of stormwater infrastructure to identify damaged systems, blocked outfalls, and failed BMPs. Property owners are expected to inspect and repair their systems promptly after storm events.

Penalty Structure

State enforcement under the SC Pollution Control Act allows civil penalties of up to $10,000 per day per violation. SCDES investigates complaints, conducts inspections, and issues enforcement actions for unpermitted activity, erosion control failures, and illegal discharges.

Georgetown County enforces local stormwater and floodplain ordinances. Violations can result in notices of violation, stop-work orders, fines, and denial of future permits. The county may also require restoration of damaged natural resources, particularly in sensitive areas along rivers and coastal marshes.

OCRM violations within the coastal zone carry additional enforcement authority. Unauthorized fill, grading, or construction in critical areas can result in mandatory removal and restoration orders, plus separate fines under the Coastal Zone Management Act.

Key BMPs

Georgetown County's flood-prone terrain and high water table shape BMP design requirements:

  • Wet detention ponds - Must be designed to withstand riverine flooding without structural failure. Outfall structures need backflow prevention to handle tidal and river backwater effects.
  • Constructed wetlands - Natural treatment systems that complement the county's existing wetland environment. Provide good pollutant removal and work with the local hydrology.
  • Bioretention with underdrains - Required in areas with high groundwater. Standard infiltration designs don't work in Georgetown's saturated soils.
  • Riparian buffers - Critical along the four river systems and their tributaries. Natural vegetated buffers are the most effective protection for Georgetown's waterways.
  • Elevated BMPs - In flood-prone areas, stormwater control structures must be designed to remain functional during flood events, with elevated control structures and flood-resistant embankments.

Local Ordinances

Georgetown County's stormwater management ordinance addresses both construction-phase and post-construction requirements. The ordinance works alongside the county's MS4 permit program and requires maintenance agreements for all permanent BMPs.

The county's floodplain management ordinance is particularly significant given the extent of flood-prone areas. Development in flood zones must comply with FEMA standards, including elevation requirements, flood-proofing for non-residential structures, and restrictions on fill in floodways. These requirements directly affect stormwater system design and placement.

Following the devastating floods of 2015, 2016 (Hurricane Matthew), 2018 (Hurricane Florence), and subsequent storms, Georgetown County has strengthened its approach to stormwater management and flood resilience. Development reviews now incorporate flood risk more prominently in stormwater system design.

Georgetown County Stormwater FAQs

How does Georgetown County's hurricane vulnerability affect stormwater regulations? expand_more
Georgetown County's location at the confluence of the Waccamaw, Pee Dee, Black, and Sampit rivers makes it extremely vulnerable to hurricane flooding. After major storms like Hurricane Florence (2018) and Hurricane Ian (2022), the county experienced catastrophic riverine flooding that overwhelmed stormwater systems for weeks. This flood history has influenced stricter floodplain management requirements and increased emphasis on stormwater system resilience in development reviews.
What is Georgetown County's MS4 stormwater permit? expand_more
Georgetown County operates under a Phase II Small MS4 NPDES permit issued by SCDES. The permit requires the county to implement stormwater management programs including public education, illicit discharge detection, construction site runoff control, post-construction stormwater management, and pollution prevention. The urbanized area around the City of Georgetown and Pawleys Island is the primary focus of MS4 requirements.
What are the stormwater penalty amounts in Georgetown County? expand_more
State penalties under the SC Pollution Control Act can reach $10,000 per day per violation. SCDES enforces these for unpermitted construction, failed erosion controls, and illegal discharges. Georgetown County enforces its local stormwater and floodplain ordinances with notices of violation and fines. The county can also deny future permits to property owners with unresolved violations.

Ready for a site that thrives?

AUE Land provides BMP inspections, erosion control, and drainage repair throughout coastal South Carolina, including Georgetown County's flood-vulnerable properties.

fact_check Site Health Audit

check_circle Structural BMP Integrity Scan
check_circle Soil Erosion Risk Analysis
check_circle Regulatory Compliance Status
check_circle Written Findings & Recommendations